casestudy-demo

Fast-Track Fire Detection System for Artemis Hospital

Project Overview

The Challenge

As Artemis Hospital prepared to become operational, a reliable and fully functional fire detection system was critical for obtaining necessary approvals and ensuring the safety of patients, staff, and visitors.

The challenge was significant:

  • Extremely aggressive project timeline of just three months.
  • Hospital opening schedule could not be delayed.
  • Installation had to be coordinated alongside multiple ongoing MEP and interior activities.
  • Zero compromise on quality, testing, and system reliability.

The hospital required a trusted partner capable of mobilizing resources quickly and delivering a complex fire detection infrastructure within a compressed schedule.

ZAP Fire's Solution

ZAP Fire deployed dedicated engineering, project management, and installation teams to execute the project on a fast-track basis.
To meet the critical deadline, our teams worked in multiple shifts, including day and night operations, ensuring continuous progress across all areas of the hospital.

Scope of Work

  • Supply, installation, testing, and commissioning of fire detection system.
  • Cable laying and network infrastructure.
  • Installation of fire alarm control panels.
  • Installation and programming of detectors.
  • System integration, testing, and commissioning.
  • Final handover and documentation.

Project Highlights

Key Numbers

14,000 meters 

of fire alarm cable laid

700 detectors

installed & commissioned

2 Fire Alarm Control Panels

integrated and programmed

3-month

project completion

24×7

execution strategy with day and night shifts

Execution Excellence

With hospital commissioning dependent on the successful completion of the fire detection system, every day counted.

ZAP Fire implemented:

  • Parallel work fronts across multiple floors.
  • Dedicated supervision teams for quality control.
  • Continuous coordination with hospital management and other contractors.
  • Daily progress monitoring and milestone tracking.
  • Round-the-clock installation activities to accelerate execution.

Despite the compressed schedule, every detector, loop, panel, and field device was thoroughly tested and commissioned to ensure system reliability from day one.

Results Delivered

Business Impact

  • Hospital fire detection system completed in a record three months.
  • Supported timely operational readiness of the hospital.
  • Enabled critical life-safety infrastructure before go-live.
  • Delivered without compromising installation quality or testing standards.
  • Established a dependable fire safety foundation for one of Gurugram’s leading healthcare facilities.

Why This Project Matters

This project demonstrates ZAP Fire’s ability to deliver mission-critical fire detection systems under demanding timelines while maintaining the highest standards of quality, safety, and execution.

When timelines are non-negotiable and safety cannot be compromised, clients trust ZAP Fire to deliver.

Project Snapshot

Achievement Table
PARAMETER ACHIEVEMENT
Industry
Healthcare
Location
Gurugram
Cable Installed
14,000 Meters
Detectors Installed
700
Fire Alarm Panels
2
Completion Period
3 Months
Execution Model
Day & Night Shifts
Outcome
Successful Hospital Go-Live Support

"14,000 meters of cabling. 700 detectors. 2 control panels. One hospital ready to save lives—delivered in just 90 days."