- Casestudy
Fast-Track Fire Detection System for Artemis Hospital
Project Overview
- Client: Artemis Hospital
- Location: Sector 51, Gurugram, Haryana
- Project Type: Fire Detection & Alarm System Installation
-
Completion Timeline: 3 Months
(Record Time)
- Executed By: ZAP Fire
The Challenge
As Artemis Hospital prepared to become operational, a reliable and fully functional fire detection system was critical for obtaining necessary approvals and ensuring the safety of patients, staff, and visitors.
The challenge was significant:
- Extremely aggressive project timeline of just three months.
- Hospital opening schedule could not be delayed.
- Installation had to be coordinated alongside multiple ongoing MEP and interior activities.
- Zero compromise on quality, testing, and system reliability.
The hospital required a trusted partner capable of mobilizing resources quickly and delivering a complex fire detection infrastructure within a compressed schedule.
ZAP Fire's Solution
ZAP Fire deployed dedicated engineering, project management, and installation teams to execute the project on a fast-track basis.
To meet the critical deadline, our teams worked in multiple shifts, including day and night operations, ensuring continuous progress across all areas of the hospital.
Scope of Work
- Supply, installation, testing, and commissioning of fire detection system.
- Cable laying and network infrastructure.
- Installation of fire alarm control panels.
- Installation and programming of detectors.
- System integration, testing, and commissioning.
- Final handover and documentation.
Project Highlights
Key Numbers
14,000 meters
of fire alarm cable laid
700 detectors
installed & commissioned
2 Fire Alarm Control Panels
integrated and programmed
3-month
project completion
24×7
execution strategy with day and night shifts
Execution Excellence
With hospital commissioning dependent on the successful completion of the fire detection system, every day counted.
ZAP Fire implemented:
- Parallel work fronts across multiple floors.
- Dedicated supervision teams for quality control.
- Continuous coordination with hospital management and other contractors.
- Daily progress monitoring and milestone tracking.
- Round-the-clock installation activities to accelerate execution.
Despite the compressed schedule, every detector, loop, panel, and field device was thoroughly tested and commissioned to ensure system reliability from day one.
Results Delivered
Business Impact
- Hospital fire detection system completed in a record three months.
- Supported timely operational readiness of the hospital.
- Enabled critical life-safety infrastructure before go-live.
- Delivered without compromising installation quality or testing standards.
- Established a dependable fire safety foundation for one of Gurugram’s leading healthcare facilities.
Why This Project Matters
This project demonstrates ZAP Fire’s ability to deliver mission-critical fire detection systems under demanding timelines while maintaining the highest standards of quality, safety, and execution.
When timelines are non-negotiable and safety cannot be compromised, clients trust ZAP Fire to deliver.
Project Snapshot
| PARAMETER | ACHIEVEMENT |
|---|---|
|
|
Healthcare |
|
|
Gurugram |
|
|
14,000 Meters |
|
|
700 |
|
|
2 |
|
|
3 Months |
|
|
Day & Night Shifts |
|
|
Successful Hospital Go-Live Support |